Project Charter

Silvanus Platform Implementation

FORMAL PROJECT AUTHORIZATION

Executive Summary

This Project Charter formally authorizes the initiation of the Silvanus Platform project for Archwood Group, establishing a unified digital infrastructure to transform business operations. The project will commence in January 2026 with a 24-month implementation timeline and a total budget of £4 million.

The Silvanus Platform will replace 12+ disparate systems with a single, intelligent platform powered by Azure cloud services and AI capabilities, achieving 75% process automation and delivering £2.5 million in annual cost savings upon full implementation.

Project Name
Silvanus Platform Implementation
Project Code
SILV-2026
Start Date
January 5, 2026
End Date
December 31, 2027
Total Budget
£4,000,000
Project Sponsor
[Executive Name]
Project Manager
[PM Name]
Charter Approval Date
[Date]

Project Purpose & Justification

1.1 Business Need

Archwood Group currently faces significant operational challenges that limit growth potential and efficiency:

1.2 Strategic Alignment

The Silvanus Platform directly supports Archwood Group's strategic objectives:

Strategic Objective Silvanus Contribution Expected Impact
Digital Transformation Cloud-native platform with AI capabilities 100% digital processes by 2028
Operational Excellence Process automation and optimization 75% reduction in manual tasks
Cost Optimization System consolidation and efficiency gains 30% reduction in operational costs
Business Growth Scalable infrastructure Support for 3x growth without proportional cost increase
Data-Driven Decisions Real-time analytics and insights 50% faster decision-making

Project Objectives & Success Criteria

2.1 Primary Objectives

🎯
Unified Platform Deployment
Replace 12+ legacy systems with single integrated platform by Q4 2026
âš¡
Process Automation
Achieve 75% automation of routine tasks by end of 2027
💰
Cost Reduction
Deliver £2.5M annual savings starting Year 2
📊
Real-time Analytics
Provide instant access to business metrics and KPIs
🤖
AI Integration
Deploy intelligent agent for automated support and decision-making

2.2 Measurable Success Criteria

Category Metric Target Measurement Method
User Adoption Active users > 90% of employees System analytics
System Performance Uptime 99.9% availability Monitoring tools
Response Time API latency < 200ms (95th percentile) Performance monitoring
Process Efficiency Task completion time 50% reduction Process analytics
User Satisfaction NPS Score > 70 Quarterly surveys
Error Rate System errors < 0.1% Error tracking
ROI Payback period < 18 months Financial analysis

Project Scope

3.1 In Scope

3.2 Out of Scope

3.3 Key Deliverables

Deliverable Description Due Date
Technical Architecture Complete system design and specifications January 31, 2026
Core Platform MVP Basic authentication, user management, APIs March 31, 2026
Pilot Deployment Limited rollout to select departments June 30, 2026
Production Release Organization-wide platform deployment September 30, 2026
AI Agent Launch Silvanus bot operational December 31, 2026
Advanced Features Analytics, automation, integrations June 30, 2027
Platform Optimization Performance tuning and scaling December 31, 2027

Project Organization & Stakeholders

4.1 Governance Structure

Executive Steering Committee

Purpose: Strategic oversight and decision-making

Meeting Frequency: Monthly

Members:

  • CEO - Final authority
  • CFO - Budget approval
  • CTO - Technical oversight
  • COO - Operational alignment
  • Project Sponsor - Direct oversight

Project Management Office

Purpose: Day-to-day project management and coordination

Meeting Frequency: Weekly

Members:

  • Project Manager - Overall project leadership
  • Technical Lead - Architecture decisions
  • Business Analyst - Requirements management
  • Change Manager - Organizational change
  • PMO Coordinator - Administrative support

4.2 Key Stakeholders

Stakeholder Role/Department Interest/Influence Engagement Strategy
Executive Team C-Suite High/High Monthly steering committee, executive briefings
Department Heads All Departments High/High Bi-weekly updates, requirements sessions
IT Department Technology High/Medium Daily collaboration, technical reviews
End Users All Employees High/Low Training sessions, feedback surveys
Finance Team Finance Medium/High Budget reviews, ROI reporting
Security Team InfoSec High/Medium Security reviews, compliance audits
External Vendors Various Low/Low Integration planning, contract management

4.3 Project Team Structure

Role Responsibilities FTE Phase
Project Manager Overall project management, stakeholder coordination 1.0 All
Technical Architect System design, technical decisions 1.0 All
Lead Developer Development team leadership, code reviews 1.0 All
Senior Developers Platform development, testing 3.0 Phase 1
DevOps Engineer Infrastructure, CI/CD, deployment 1.0 All
AI/ML Engineer Silvanus agent development 1.0 Phase 2+
Business Analyst Requirements gathering, documentation 1.0 All
QA Engineers Testing, quality assurance 2.0 Phase 2+
Change Manager Organizational change, training 1.0 Phase 3+

Project Timeline & Milestones

5.1 Major Milestones

Q1 2026
Foundation & Architecture
Complete technical architecture, team formation, development environment setup, and initial infrastructure deployment
Q2 2026
MVP Development
Core platform development including authentication, user management, basic APIs, and initial workflow capabilities
Q3 2026
Pilot Deployment
Limited rollout to 2-3 departments, user feedback collection, performance optimization, and bug fixes
Q4 2026
Production Release
Organization-wide deployment, legacy system integration, full user training, and support establishment
Q1-Q2 2027
Advanced Features
AI agent deployment, advanced analytics, complex workflow automation, and third-party integrations
Q3-Q4 2027
Optimization & Scale
Performance optimization, multi-tenant capabilities, advanced features, and platform maturity

Budget & Resources

6.1 Budget Overview

Total Budget
£4.0M
Year 1 (2026)
£1.75M
Year 2 (2027)
£2.25M

6.2 Budget Breakdown

Category Year 1 (2026) Year 2 (2027) Total
Personnel Costs £1,200,000 £1,500,000 £2,700,000
Infrastructure (Azure) £300,000 £400,000 £700,000
Software Licenses £150,000 £200,000 £350,000
Training & Change Management £100,000 £150,000 £250,000
Total £1,750,000 £2,250,000 £4,000,000

6.3 Return on Investment

Financial Benefits

  • Annual Cost Savings: £2.5M from Year 2
  • Payback Period: 18 months
  • 5-Year NPV: £8.2M
  • IRR: 62%

Risk Management

7.1 Key Risks & Mitigation

Technical Complexity

Risk: Underestimating integration complexity with 12+ legacy systems

Impact: High

Probability: Medium

Mitigation: Phased integration approach, dedicated integration team, proven patterns, external expertise engagement

Change Resistance

Risk: User adoption challenges and organizational resistance

Impact: High

Probability: Medium

Mitigation: Comprehensive change management program, executive sponsorship, quick wins demonstration, champion network

Resource Constraints

Risk: Difficulty recruiting skilled technical resources

Impact: Medium

Probability: High

Mitigation: Early recruitment, competitive packages, contractor partnerships, knowledge transfer programs

Scope Creep

Risk: Uncontrolled expansion of project scope

Impact: Medium

Probability: Medium

Mitigation: Clear scope definition, change control process, regular stakeholder alignment, prioritization framework

Technology Risk

Risk: Selected technologies don't meet requirements

Impact: Low

Probability: Low

Mitigation: Proven technology stack, Azure partnership, POC validation, architectural flexibility

Security Breach

Risk: Security vulnerabilities in new platform

Impact: High

Probability: Low

Mitigation: Security-by-design, regular audits, penetration testing, compliance frameworks

Communication Plan

8.1 Communication Strategy

Audience Method Frequency Owner
Steering Committee Formal presentation Monthly Project Manager
Project Team Stand-up meetings Daily Scrum Master
Department Heads Status reports Bi-weekly Project Manager
All Employees Email newsletter Monthly Change Manager
IT Department Technical briefings Weekly Technical Lead
External Stakeholders Quarterly updates Quarterly Project Sponsor

8.2 Reporting Structure

Change Management

9.1 Change Management Approach

The success of the Silvanus Platform depends heavily on user adoption and organizational change. Our change management strategy includes:

Awareness Phase (Q4 2025 - Q1 2026)

  • Executive town halls to communicate vision and benefits
  • Department briefings on upcoming changes
  • Intranet site with project information and FAQs
  • Change champion network establishment

Preparation Phase (Q2 - Q3 2026)

  • Skills gap analysis and training needs assessment
  • Training curriculum development
  • Pilot user group selection and preparation
  • Process documentation and updating

Implementation Phase (Q4 2026 - Q2 2027)

  • Comprehensive user training programs
  • Super-user certification
  • Floor-walking support during go-live
  • Feedback collection and rapid response

Reinforcement Phase (Q3 - Q4 2027)

  • Continuous improvement based on feedback
  • Success story sharing
  • Advanced feature training
  • Benefits realization tracking

Assumptions & Constraints

10.1 Key Assumptions

10.2 Constraints

Dependencies

Dependency Type Impact Management Strategy
Azure Environment Setup Technical Critical path Early engagement with Azure team
Legacy System Documentation Information Integration design Documentation audit in Q4 2025
Security Approval Compliance Go-live gate Early security architecture review
User Training Completion Organizational Adoption success Phased training approach
Data Migration Technical Cutover planning Incremental migration strategy

Project Charter Approval

By signing this Project Charter, the undersigned acknowledge they have reviewed the Project Charter and agree with the approach, objectives, and responsibilities documented herein.

Project Sponsor
Name: _______________________
Title: _______________________
Date: _______________________
Signature: __________________
Chief Executive Officer
Name: _______________________
Title: CEO
Date: _______________________
Signature: __________________
Chief Financial Officer
Name: _______________________
Title: CFO
Date: _______________________
Signature: __________________
Chief Technology Officer
Name: _______________________
Title: CTO
Date: _______________________
Signature: __________________
Project Manager
Name: _______________________
Title: Project Manager
Date: _______________________
Signature: __________________
Chief Information Security Officer
Name: _______________________
Title: CISO
Date: _______________________
Signature: __________________